2 tunnels, total length of 350m
Scope of works:
delivery of RGNN switchboard
control cabinet
basic lighting wiring
emergency lighting installation
automation system installation
fire alarm system installation
phone line installation
low-voltage installations
television monitoring installation
Preparation of transformer station:
delivery and installation of transformers 8x1,6 KVA
delivery and installation of switchboards LV 3200A from LV1 to LV7
Siemens bus bars
Execution of the complete wiring:
for technology
automation and control
water treatment station
administration building, facility building and warehouse-workshop
Preparation of electric installations for the production line of MDF boards.
Modernisation of GSZ station, 110/6kV, which includes:
preparation of the billing setup on the voltage110kV
change of the security systems of 2 transformers 110/6/6kV
Lightning and sockets installation in the halls G and H.
Preparation of the electric installation for additional worksites for lading of goods.
Preparation of electric and installation works.